Exhibit 4
FILED: NEWID: 4CFFFD1A-33AF-40CF-9556-0501EF3807D3
YORK COUNTY CLERK 06/12/2024 09:02 AM INDEX NO. 652977/2024
DocuSign Envelope 824BA422-B404-4AFC-A1CC-8E19530B73A2
NYSCEF DOC. NO. 6 RECEIVED NYSCEF: 06/12/2024
A Terran Orbital Corporation ASTRA
Response to:
Tyvak Nano-Satellite Systems, Inc.
for
Change Order #1 to Terran Orbital + Astra
Tranche 1 Contract
Submitted: October 18, 2022
Delivered to:
Nirav Mehta | nirav.mehta@terranorbital.com
From:
Margo De Naray | mdenaray@astra.com
Astra Space Operations, Inc.
1900 Skyhawk St., Alameda, CA, 94501
The information contained in this response and any files/attachments transmitted with
it are proprietary to Astra Space, Inc. and are intended only for the addressee. Access
to this email by anyone else is unauthorized. If you received this response in error,
please contact the sender immediately and delete the material from your computer.
Additionally, this email and/or its attachments may contain technical data whose export
is restricted by the U.S. Department of State under the International Traffic in Arms
Regulations (ITAR). Licenses approved by the Department of State are required prior to
the export of ITAR-controlled technical data to any foreign person or organization either
in the United States or abroad.
FILED: NEWID: 4CFFFD1A-33AF-40CF-9556-0501EF3807D3
YORK COUNTY CLERK 06/12/2024 09:02 AM INDEX NO. 652977/2024
DocuSign Envelope 824BA422-B404-4AFC-A1CC-8E19530B73A2
NYSCEF DOC. NO. 6
ASTRA RECEIVED NYSCEF: 06/12/2024
System Configuration
Astra is pleased to submit Change Order #1 to the Terran Orbital + Astra
Tranche 1 Contract, fully executed on October 17th, 2022. Tyvak requests
the total quantity of Flight Models (FM) be reduced from 44 (42 FM and
2 spares) to 42 (42 FM and no spares). In addition, Tyvak requests the
total quantity of Engineering Development Units (EDUs) be reduced from
3 to 2.
Aside from the following, all other contract terms are to remain the
same. See below for pricing updates.
Pricing Updates
Item Unit Price Previous Updated Subtotal
Qty Qty
Flight Models $248,000 42 42 $10,416,000
Spares $248,000 2 0 $0
EDU $150,000 3 2 $300,000
Total Updated Fixed $10,716,000
Price
Milestone Payment Schedule
Estimated
Milestone
Completion Milestone Milestone
Milestone Description Date* Payment % Payment ($)
Contract Signing 10/11/2022 26.5% $2,840,500
Kickoff & data package 10/25/2022 26.5% $2,840,500
Engineering Model (EDU) 1/31/2023 10% $1,071,600
Design Review & data 2/28/2023 10% $1,071,600
packages
DRB & data packages 5/31/2023 5% $535,800
Flight Model (FM) 1-5 8/31/2023 5% $535,800
Flight Model (FM) 6-15 9/30/2023 5% $535,800
Flight Model (FM) 16-25 10/31/2023 5% $535,800
Flight Model (FM) 26-35 11/30/2023 5% $535,800
Flight Model (FM) 36-42 12/31/2023 2% $212,800
Total Payments 100% $10,716,000
*Astra may deliver up to 60 days early for each milestone and associated
payment will be due at that time.
©️ 2022 Astra Space Operations, Inc., Commercial proprietary information. This document
shall not be reproduced, duplicated, or disclosed in whole or in part without prior
approval from Astra Inc. authorized personnel. 2
FILED: NEWID: 4CFFFD1A-33AF-40CF-9556-0501EF3807D3
YORK COUNTY CLERK 06/12/2024 09:02 AM INDEX NO. 652977/2024
DocuSign Envelope 824BA422-B404-4AFC-A1CC-8E19530B73A2
NYSCEF DOC. NO. 6
ASTRA RECEIVED NYSCEF: 06/12/2024
Termination Liability Schedule
Monthly Monthly Cumulative
Liability Liability Liability
Milestone Description Month % ($)
Contract Signing, 10/1/2022 60% $6,429,600 $6,429,600
Kickoff & data package
11/1/2022 3% $321,480 $6,751,080
12/1/2022 3% $321,480 $7,072,560
Engineering Model 1/1/2023 3% $321,480 $7,394,040
(EDU)
Design Review & data 2/1/2023 8% $857,280 $8,251,320
packages
3/1/2023 1% $107,160 $8,358,480
4/1/2023 1% $107,160 $8,465,640
DRB & data packages 5/1/2023 1% $107,160 $8,572,800
6/1/2023 1% $107,160 $8,679,960
7/1/2023 1% $107,160 $8,787,120
Flight Model (FM) 1-5 8/1/2023 1% $107,160 $8,894,280
Flight Model (FM) 6-15 9/1/2023 4% $455,430 $9,349,710
Flight Model (FM) 16- 10/1/2023 4% $455,430 $9,805,140
25
Flight Model (FM) 26- 11/1/2023 4% $455,430 $10,260,570
35
Flight Model (FM) 36-42 12/1/2023 4% $455,430 $10,716,000
©️ 2022 Astra Space Operations, Inc., Commercial proprietary information. This document
shall not be reproduced, duplicated, or disclosed in whole or in part without prior
approval from Astra Inc. authorized personnel. 3
FILED: NEWID: 4CFFFD1A-33AF-40CF-9556-0501EF3807D3
YORK COUNTY CLERK 06/12/2024 09:02 AM INDEX NO. 652977/2024
DocuSign Envelope 824BA422-B404-4AFC-A1CC-8E19530B73A2
NYSCEF DOC. NO. 6
ASTRA RECEIVED NYSCEF: 06/12/2024
Tyvak Nano-Satellite Systems, Inc. Astra Space Operations, Inc.
By: _____________________________ By: _______________________________
FUEU AU24U34t5b...
Marc Bell
Name:___________________________ Name: Margo de Naray
President
Title: ____________________________ Title: VP, Mission Management & Customer Experience
11/03/2022 10/20/2022
Date: ____________________________ Date: ______________________________
©️ 2022 Astra Space Operations, Inc., Commercial proprietary information. This document
shall not be reproduced, duplicated, or disclosed in whole or in part without prior
approval from Astra Inc. authorized personnel. 4