On July 21, 2016 a
Judgment
was filed
involving a dispute between
Allison Offshore Services Ii Llc,
Jab Energy Solutions Ii Llc,
Offshore Domestic Group, Llc,
and
Alliance Energy Services, Llc,
Fairways Offshore Exploration Inc,
Offshore Domestic Group Llc,
Offshore Specialty Fabricators Inc,
Allison Offshore Services Ii Llc,
Jab Energy Solutions Ii Llc,
for Debt/Contract - Debt/Contract
in the District Court of Harris County.
Preview
CAUSE NO. 2016 48155
JAB ENERGY SOLUTIONS II, IN THE DISTRICT COURT OF
LLC AND ALLISON OFFSHORE
SERVICES II, LLC
HARRIS COUNTY, TEXAS
OFFSHORE SPECIALTY
FABRICATORS, INC. AND
FAIRWAY OFFSHORE
EXPLORATION, INC. JUDICIAL DISTRICT
PARTIAL SUMMARY JUDGMENT
On this day, the Court considered Defendant/Counter Plaintiff Offshore Specialty
Fabricator, LLC’s (“OSF”) Motion for Partial Summary Judgment against Plaintiff/Counter
Defendant JAB Energy Solutions II, LLC (“JAB”). After reviewing the motion, JAB’s response,
if any, the evidence and pleadings on file, and the arguments
of counsel, the Court finds that the
motion
for partial summary judgment is well taken and should be granted. It is therefore,
ORDERED that OSF’s Motion for Partial Summary Judgment against JAB is hereby
GRANTED. It is further,
ORDERED that Offshore Specialty Fabricator, LLC shall have judgment against and
recover from JAB Energy Solutions II, LLC the following:
Damages in the principal sum of Four Million Five Hundred One Thousand Nine
Hundred Two and 02/100 Dollars ($4,501,902.02
Pre judgment interest at the rate of Six Percent (6%),per annum on the principal
sum of Four Million Five Hundred One Thousand Nine Hundred Two and 02/100
Dollars ($4,501,902.02) starting on December 23, 2015. This amounts to $740.03
per day beginning
on December 23, 2015 until the date this judgmentis signed;
and
Post judgment interest on the unpaid balance of this Judgment at the rate of five
percent (%) perannum. from the date this Judgment is signed until this Judgment
is fully and finally paid. It is further,
ORDERED that all Offshore Specialty Fabricator, LLC’s costs of court associated with
its counter claim are assessed against JAB Energy Solutions II, LLC. It is further,
ORDERED that all writs and processes for the enforcement and collection of this
Judgment
or the costs of court may issue as necessary and when appropriate.
SIGNED this day of , 2017
JUDGE PRESIDING
Document Filed Date
February 02, 2017
Case Filing Date
July 21, 2016
Category
Debt/Contract - Debt/Contract
For full print and download access, please subscribe at https://www.trellis.law/.