Case Last Refreshed: 7 months ago
Carlson & Co., Dmc Plumbing Contractors, Fort Hill Construction Inc., filed a(n) Breach of Contract - Commercial case represented by Mehta Ravi R., Mehta Ravi Rajesh, against Carlson & Co., Covello Plastering, Dmc Plumbing Contractors, Erickson Roofing Co., Gordon L. Alatorre Masonry, (total of 10) See All represented by Armijo Mark Steven, Boardman Nora Rufail, Correll Deborah Ann, Klawunder Nina Djanbatian, Morrison Edward F, (total of 7) See All in the jurisdiction of Los Angeles County. This case was filed in Los Angeles County Superior Courts Santa Monica Courthouse with Gerald Rosenberg presiding.
Case Number |
Time To Management187 days |
|
Filing DateJune 29, 2018 |
CategoryBreach Contract/Warnty-Negligence (General Jurisdiction) |
|
Last RefreshedOctober 07, 2023 |
Practice AreaCommercial |
|
Filing LocationLos Angeles County, CA |
Matter TypeBreach of Contract |
|
Filing Court HouseSanta Monica Courthouse |
Case Outcome TypeUnknown Disposition |
Minute Order ((Case Management Conference;))
Date: 2019-01-02T00:00:00Request for Dismissal
Date: 2019-03-06T00:00:00Second Amended Complaint
Date: 2018-08-29T00:00:00Notice and Acknowledgment of Receipt
Date: 2019-03-01T00:00:00Second Amended Complaint
Date: 2018-08-29T00:00:00Request for Dismissal
Date: 2019-04-25T00:00:00Request for Dismissal
Date: 2019-09-10T00:00:00Notice of Settlement
Date: 2019-06-18T00:00:00Summons Filed
Date: 2018-06-29T00:00:00First Amended Complaint
Date: 2018-08-21T00:00:00Application for Determination of Good Faith Settlement
Date: 2019-03-01T00:00:00Civil Case Cover Sheet
Date: 2018-06-29T00:00:00Second Amended Complaint
Date: 2018-06-29T00:00:00Proof of Service by Mail
Date: 2019-04-26T00:00:00Proof of Personal Service
Date: 2019-03-12T00:00:00Complaint
Date: 2018-06-29T00:00:00Summons
Date: 2018-08-29T00:00:00Notice (NOTICE OF CASE ASSIGNMENT )
Date: 2018-06-29T00:00:00Notice of Ruling During Case Management Conference
Date: 2019-01-02T00:00:00Case Management Statement
Date: 2018-12-21T00:00:00Case Management Statement
Date: 2019-06-07T00:00:00Minute Order ( (Order to Show Cause Re: Dismissal as to Settled Parties; Hear...))
Date: 2019-09-09T00:00:00ANSWER OF DMC PLUMBING CONTRACTOR, INC. TO PLAINTIFF?S COMPLAINT
Date: 2019-03-21T00:00:00Answer
Date: 2019-03-08T00:00:00Notice of Ruling
Date: 2019-09-10T00:00:00Notice of Ruling
Date: 2019-01-15T00:00:00Proof of Service by Substituted Service
Date: 2019-03-12T00:00:00Minute Order ( (Case Management Conference))
Date: 2019-06-19T00:00:00Notice and Acknowledgment of Receipt
Date: 2019-03-26T00:00:00Ex Parte Application (for Order Granting Application for Determination of Good Faith Settlement)
Date: 2019-09-05T00:00:00Case Management Statement
Date: 2019-06-10T00:00:00Notice of Settlement
Date: 2019-03-01T00:00:00Minute Order ( (Order to Show Cause Re: Dismissal as to Settled Parties))
Date: 2019-10-10T00:00:00First Amended Complaint
Date: 2018-08-21T00:00:00Answer
Date: 2019-04-02T00:00:00Order to Show Cause re: Dismissal (Settlement)
Date: 2019-12-04T00:00:00Notice of Posting of Jury Fees
Date: 2019-06-27T00:00:00Notice of Posting of Jury Fees
Date: 2019-06-26T00:00:00Answer
Date: 2019-03-26T00:00:00Request for Dismissal
Date: 2019-05-23T00:00:00Notice of Change of Firm Name
Date: 2019-10-04T00:00:00Request for Dismissal
Date: 2020-01-08T00:00:00Declaration in Support of Ex Parte Application
Date: 2019-09-05T00:00:00Case Management Statement
Date: 2019-03-14T00:00:00Case Management Statement
Date: 2019-04-02T00:00:00Notice of Ruling
Date: 2019-06-19T00:00:00Notice of Ruling
Date: 2019-04-04T00:00:00Notice of Settlement
Date: 2019-11-26T00:00:00Request for Dismissal
Date: 2019-10-09T00:00:00Case Management Statement
Date: 2019-03-22T00:00:00Minute Order ( (Order to Show Cause Re: Dismissal (Settlement)))
Date: January 22, 2020Application for Determination of Good Faith Settlement
Date: 2019-06-18T00:00:00Request for Dismissal
Date: 2019-12-30T00:00:00Request for Dismissal
Date: 2019-10-24T00:00:00DMC PLUMBING CONTRACTOR, INC.'S DEMAND FOR JURY TRIAL
Date: 2019-03-21T00:00:00Minute Order ( (Case Management Conference))
Date: 2019-04-03T00:00:00Answer
Date: 2019-03-22T00:00:00Request for Dismissal
Date: 2019-10-08T00:00:00Summons Filed (SECOND AMENDED COMPLAINT )
Date: 2018-08-29T00:00:00Notice
Date: 2018-06-29T00:00:00Summons
Date: 2018-06-29T00:00:00Order (Proposed Order Granting Good Faith Settlement of Fort Hill Construction, Inc.)
Date: 2019-03-11T00:00:00Proof of Personal Service
Date: 2019-03-01T00:00:00Request for Dismissal
Date: 2019-09-18T00:00:00Proof of Service by Mail
Date: 2019-03-14T00:00:00Cross-Complaint (of DMC Plumbing Contractor, Inc.)
Date: 2019-03-21T00:00:00Notice of Case Reassignment and Order for Plaintiff to Give Notice
Date: 2019-04-22T00:00:00Notice Re: Continuance of Hearing and Order
Date: 2019-12-23T00:00:00Proof of Service by Mail
Date: 2019-03-22T00:00:00Statement of the Case
Date: 2019-08-22T00:00:00Case Management Statement
Date: 2019-06-03T00:00:00Case Management Statement
Date: 2019-10-04T00:00:00Civil Case Cover Sheet
Date: June 29, 2018Summons
Date: June 29, 2018Legacy Document - LEGACY DOCUMENT TYPE: First Amended Complaint
Date: August 21, 2018Amended Complaint - First
Date: August 21, 2018Complaint -
Date: August 29, 2018Minute Order - Minute Order (Case Management Conference;)
Date: January 02, 2019Summons -
Date: August 29, 2018Notice of Ruling - Notice of Ruling During Case Management Conference
Date: January 02, 2019Notice of Ruling
Date: January 15, 2019Application for Determination of Good Faith Settlement
Date: March 01, 2019Notice of Settlement
Date: March 01, 2019Notice and Acknowledgment of Receipt
Date: March 01, 2019Request for Dismissal
Date: March 06, 2019Proof of Personal Service
Date: March 01, 2019Answer
Date: March 08, 2019Proof of Personal Service
Date: March 12, 2019Proof of Service by Substituted Service
Date: March 12, 2019Proof of Service by Mail
Date: March 14, 2019Case Management Statement
Date: March 14, 2019Demand for Jury Trial - DMC PLUMBING CONTRACTOR, INC.'S DEMAND FOR JURY TRIAL
Date: March 21, 2019Cross-Complaint
Date: March 21, 2019Answer - ANSWER OF DMC PLUMBING CONTRACTOR, INC. TO PLAINTIFF’S COMPLAINT
Date: March 21, 2019Proof of Service by Mail
Date: March 22, 2019Answer
Date: March 22, 2019Case Management Statement
Date: March 22, 2019Notice and Acknowledgment of Receipt
Date: March 26, 2019Case Management Statement
Date: April 02, 2019Answer
Date: March 26, 2019Answer
Date: April 02, 2019Minute Order - MINUTE ORDER (CASE MANAGEMENT CONFERENCE)
Date: April 03, 2019Notice of Ruling
Date: April 04, 2019Notice of Case Reassignment and Order for Plaintiff to Give Notice
Date: April 22, 2019Request for Dismissal
Date: April 25, 2019Proof of Service by Mail
Date: April 26, 2019Request for Dismissal
Date: May 23, 2019Case Management Statement
Date: June 03, 2019Case Management Statement
Date: June 07, 2019Case Management Statement
Date: June 10, 2019Application for Determination of Good Faith Settlement
Date: June 18, 2019Notice of Settlement
Date: June 18, 2019Minute Order - MINUTE ORDER (CASE MANAGEMENT CONFERENCE)
Date: June 19, 2019Notice of Ruling
Date: June 19, 2019Notice of Posting of Jury Fees
Date: June 26, 2019Notice of Posting of Jury Fees
Date: June 27, 2019Statement of the Case
Date: August 22, 2019Declaration in Support of Ex Parte Application
Date: September 05, 2019Minute Order - MINUTE ORDER (ORDER TO SHOW CAUSE RE: DISMISSAL AS TO SETTLED PARTIES; HEAR...)
Date: September 09, 2019Request for Dismissal
Date: September 10, 2019Notice of Ruling
Date: September 10, 2019Request for Dismissal
Date: September 18, 2019Notice of Change of Firm Name
Date: October 04, 2019Request for Dismissal
Date: October 08, 2019Case Management Statement
Date: October 04, 2019Minute Order - MINUTE ORDER (ORDER TO SHOW CAUSE RE: DISMISSAL AS TO SETTLED PARTIES)
Date: October 10, 2019Request for Dismissal
Date: October 24, 2019Notice of Settlement
Date: November 26, 2019Order to Show Cause re: Dismissal (Settlement)
Date: December 04, 2019Notice Re: Continuance of Hearing and Order
Date: December 23, 2019Request for Dismissal
Date: December 30, 2019Minute Order - MINUTE ORDER (ORDER TO SHOW CAUSE RE: DISMISSAL (SETTLEMENT))
Date: January 22, 2020Minute Order ((Case Management Conference;))
Date: 2019-01-02T00:00:00Cross-Complaint (of DMC Plumbing Contractor, Inc.)
Date: 2019-03-21T00:00:00Summons Filed (SECOND AMENDED COMPLAINT )
Date: 2018-08-29T00:00:00Notice (NOTICE OF CASE ASSIGNMENT )
Date: 2018-06-29T00:00:00Order (Proposed Order Granting Good Faith Settlement of Fort Hill Construction, Inc.)
Date: 2019-03-11T00:00:00Minute Order ( (Case Management Conference))
Date: 2019-06-19T00:00:00Minute Order ( (Order to Show Cause Re: Dismissal as to Settled Parties))
Date: 2019-10-10T00:00:00Minute Order ( (Order to Show Cause Re: Dismissal (Settlement)))
Date: January 22, 2020Minute Order ( (Order to Show Cause Re: Dismissal as to Settled Parties; Hear...))
Date: 2019-09-09T00:00:00Minute Order ( (Case Management Conference))
Date: 2019-04-03T00:00:00Ex Parte Application (for Order Granting Application for Determination of Good Faith Settlement)
Date: 2019-09-05T00:00:00Order to Show Cause re: Dismissal (Settlement)
Date: 2019-12-04T00:00:00For full print and download access, please subscribe at https://www.trellis.law/.