Case Last Refreshed: 3 months ago
Andrea Ferreira, Joseph Ferreira, filed a(n) Mass Torts - Torts case represented by Belluck, Joseph Warren, against 3M Company, Individually And As Successor To Minnesota Mining And Manufacturing Company, Allied Building Products Corp., American Biltrite, Inc., Individually And Successor To Amtico Floors, At&T Corp., Individually And As Successor To The New Jersey Bell Telephone Company And The Chesapeake And Potomac Telephone Company, Bradco Supply, Now American Builders & Contractors Supply Co., Inc., (total of 52) See All represented by Brown, Robert Dorrance, Cook, Kerryann Marie, Coughlan, Timothy, Digregorio, Joseph, Dilonardo, Anna M., (total of 31) See All in the jurisdiction of New York County. This case was filed in New York County Superior Courts with Adam Silvera presiding.
Case Number |
|
Filing DateOctober 19, 2023 |
CategoryTorts - Asbestos |
Last RefreshedJanuary 24, 2024 |
Practice AreaTorts |
Filing LocationNew York County, NY |
Matter TypeMass Torts |
This complaint was filed in the Supreme Court of the State of New York, County of New York. The plaintiffs, Joseph Ferreira and Andrea Ferreira, are suing multiple defendants, including Allied Building Products Corp., American Biltrite, Inc., AT&T Co...
At&T Corp., Individually And As Successor To The New Jersey Bell Telephone Company And The Chesapeake And Potomac Telephone Company
Builders Firstsource Inc., Individually And As Successor To Probuilding Holdings Llc, Strober Organization, Inc., A K A Strober Building Supply Inc., And Strober Bros. Inc.
Builders Firstsource - Northeast Group, Llc. , Individually And As Successor To Probuilding Holdings Llc, Strober Organization, Inc., A K A Strober Building Supply Inc., And Strober Bros. Inc.
Domco Products Texas, Inc., D B A Tarkett, Inc., Individually And As Successor To Azrock Industries, Inc.
Fidelity Capital Inc., Individually And As Successor To Strober Organization Inc., A K A Strober Building Supply Inc., And Strober Bros., Inc.
Honeywell International, Inc. Individually And F K A Alliedsignal, Inc., And As Successor-In-Interest To The Bendix Corp.
International Paper Company F K A Hammermill Paper Co. And Individually And As Successor To Us Plywood
Paramount Global, F K A Viacomcbs Inc., F K A Cbs Corporation, A Delaware Corporation, F K A Viacom Inc., Successor By Merger To Cbs Corporation, A Pennsylvania Corporation, F K A Westinghouse Electric Corporation
Probuild Company Llc, Individually And As Successor To Strober Building Supply, Llc. F K A Strober Building Supply Inc., Strober Organization, Inc., And Strober Bros., Inc.
Probuild Holdings Llc, Individually And As Successor To Strober Organization Inc., A K A Strober Building Supply Inc., And Strober Bros. Inc.
Strober Building Supply, Llc., F K A Strober Building Supply Inc., Individually And As Successor To Strober Organization Inc., Strober Building Material Centers, Inc., Strober King Building Supply Centers, Inc., Strober-Moores Building Supply Centers, Inc., And Strober Bros., Inc.
SUMMONS (PRE RJI) (AMENDED)
Date: December 06, 2023ANSWER
Date: December 07, 2023ANSWER
Date: December 01, 2023ANSWER WITH CROSS-CLAIM(S)
Date: November 30, 2023ANSWER
Date: January 08, 2024PROOF OF SERVICE
Date: January 02, 2024ADDENDUM - GENERAL (840A)
Date: January 03, 2024ORDER - NO OPP SUMMARY JUDGMENT (PROPOSED)
Date: December 21, 2023ANSWER
Date: December 22, 2023RJI -RE: NOTICE OF MOTION (Motion #001)
Date: January 03, 2024ORDER - NO OPP SUMMARY JUDGMENT (PROPOSED)
Date: December 20, 2023ACKNOWLEDGEMENT OF SERVICE
Date: December 27, 2023DEMAND FOR:
Date: December 20, 2023SUMMONS (PRE RJI) (AMENDED)
Date: November 27, 2023EXHIBIT(S) - A (Motion #001)
Date: January 03, 2024ORDER - NO OPP SUMMARY JUDGMENT (PROPOSED)
Date: December 20, 2023ANSWER
Date: November 27, 2023ANSWER
Date: December 12, 2023ANSWER
Date: December 27, 2023ANSWER WITH CROSS-CLAIM(S)
Date: November 20, 2023ANSWER
Date: December 22, 2023SUMMONS (PRE RJI) (AMENDED)
Date: November 17, 2023ANSWER
Date: November 20, 2023ANSWER
Date: November 17, 2023ANSWER
Date: December 07, 2023NOTICE OF DISCONTINUANCE (PRE RJI)
Date: November 15, 2023ANSWER
Date: November 14, 2023ANSWER
Date: November 14, 2023ANSWER
Date: November 02, 2023PRE-TRIAL DOCUMENT(S)
Date: November 13, 2023ANSWER WITH CROSS-CLAIM(S)
Date: November 15, 2023ANSWER
Date: November 13, 2023ACKNOWLEDGEMENT OF SERVICE
Date: November 10, 2023ANSWER
Date: January 09, 2024ANSWER
Date: January 10, 2024NOTICE OF MOTION (Motion #001)
Date: January 03, 2024AFFIDAVIT OR AFFIRMATION IN SUPPORT OF MOTION (Motion #001)
Date: January 03, 2024ANSWER
Date: January 02, 2024ORDER - NO OPP SUMMARY JUDGMENT (PROPOSED)
Date: December 20, 2023ANSWER WITH CROSS-CLAIM(S)
Date: December 20, 2023ANSWER
Date: December 07, 2023ANSWER
Date: December 12, 2023COMPLAINT (AMENDED)
Date: November 29, 2023ANSWER
Date: November 28, 2023ANSWER
Date: November 27, 2023ANSWER WITH CROSS-CLAIM(S)
Date: November 27, 2023ANSWER
Date: November 17, 2023STATEMENT OF AUTHORIZATION FOR ELECTRONIC FILING
Date: November 16, 2023ANSWER WITH CROSS-CLAIM(S)
Date: November 15, 2023SUMMONS (PRE RJI) (AMENDED)
Date: November 15, 2023ANSWER WITH CROSS-CLAIM(S)
Date: November 15, 2023COMPLAINT (AMENDED)
Date: November 15, 2023AFFIRMATION/AFFIDAVIT OF SERVICE
Date: November 15, 2023PRE-TRIAL DOCUMENT(S)
Date: November 13, 2023STATEMENT OF AUTHORIZATION FOR ELECTRONIC FILING
Date: October 19, 2023EXHIBIT(S) - A PLAINTIFFS INITIAL FACT SHEET Redacted per 22 NYCRR
Date: October 19, 2023SUMMONS + COMPLAINT
Date: October 19, 2023Date | Type | Description | |
---|---|---|---|
January 10, 2024 |
ANSWER On Behalf of Dykes Lumber Company |
||
January 09, 2024 | Answer | ||
January 08, 2024 |
ANSWER VERIFIED ANSWER TO THIRD AMENDED COMPLAINT- BUILDERS |
||
January 03, 2024 | ADDENDUM - GENERAL (840A) | ||
January 03, 2024 |
RJI -RE: NOTICE OF MOTION (Motion #001) Strober's Notice of Motion for Stay |
||
January 03, 2024 |
EXHIBIT(S) - A (Motion #001) Order of Liquidation |
||
January 03, 2024 |
NOTICE OF MOTION (Motion #001) Strober's Notice of Motion for Stay |
||
January 03, 2024 |
AFFIDAVIT OR AFFIRMATION IN SUPPORT OF MOTION (Motion #001) Strober's Affirmation in Support of Motion for Stay of Proceedings |
||
January 02, 2024 | PROOF OF SERVICE | ||
January 02, 2024 |
ANSWER Kohler Co.'s Answer |
For full print and download access, please subscribe at https://www.trellis.law/.