arrow left
arrow right
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
  • Revoli Construction Co., Inc. vs. City Of Melrose Certiorari Action, G. L. c. 249 § 4 document preview
						
                                

Preview

COMMONWEALTH OF MASSACHUSETTS MIDDLESEX, ss. SUPERIOR COURT CIVIL ACTION NO. 12-02061-A REVOLI CONSTRUCTION CO., INC., Plaintiff vs. CITY OF MELROSE, Defendant and CITY OF MELROSE, Third-party plaintiff ys. KLEINFELDER/SEA CONSULTANTS, INC., Third-party defendant MEMORANDUM OF DECISION AND ORDER ON CROSS MOTIONS FOR ‘ SUMMARY JUDGMENT This action arises out of a contract dispute between Revoli Construction Co., Inc. (Revoli” , the City of Melrose (“City”), and Kleinfelder/SEA Consultants (“Kleinfelder” or “Engineer”). Revoli’s two-count Complaint sets forth claims for breach of contract (“Count I”) and quantum meruit (“Count II”). Now before the court is Revoli’s Motion for Partial Summary Judgment on Liability and the City and Kleinfelder’s (collectively, “Defendants”)' Motion for Summary Judgment pursuant to Mass. R. Civ. P. 56(c). For the reasons stated herein, the Defendants’ Motion for Summary Judgment will be ALLOWED and Revoli’s motion will be DENIED. ' The Court allowed Kleinfelder’s motion to join the City’s Motion for Summary Judgment and the City’s opposition to Revoli’s Motion for Partial Summary Judgment on October 13, 2015.SUMMARY JUDGMENT RECORD Where, as here, there are cross motions for summary judgment, the court will assess the record in the light most favorable to the party against whom judgment will enter. Epstein v. Board of Appeal of Boston, 77 Mass. App. Ct. 752, 756 (2010). Accordingly, the summary judgment record, viewed in the light most favorable to Revoli contains the following facts material to this motion. Some facts are reserved for discussion, below. I. , Background In November 2010, the City commenced a project called the East Side Interceptor Sewer Relocation Project (“Project”). By way of the Project, the City sought to perform significant work on the drainage and sewer systems below the Melrose High School football field. The City hired Kleinfelder to provide engineering and consulting services for the Project. One of Kleinfelder’s duties was to prepare the specifications that prospective contractors would use to create their bids (“Bid Specifications”). -Pursuant to the preparation of the Bid Specifications, Kleinfelder collected data from geotechnical borings used to identify subsurface materials at the Project site. This data was recorded on logs that were included in the Bid Specification appendix (“Kleinfelder boring logs”). The Bid Specifications warned potential contractors that the Kleinfelder boring logs were offered “solely for the purpose of placing the Contractor in receipt of all information available.” The Bid Specifications also provided significant guidelines with regard to the installation of helical piles, which the Project required to support an underground sewer pipe.? The Bid Specifications required the contractor to furnish “all necessary engineering and design services, supervision, labor, tools, materials, and equipment to perform all work necessary to provide [a] 2 Helical piles are steel rods that screw into the ground beneath the subsurface to hold an object or structure on top.helical pile foundation system to support [the underground sewer pipe] per the specifications” described herein.” The Bid Specifications stated that the Kleinfelder boring logs “shall be used as the basis for Helical Pile design,” and that the Kleinfelder boring logs attached to the Bid Specifications “shall be considered to be representative of the in-situ subsurface conditions likely to be encountered on the project site.” (Emphasis added). Helical piles must reach particular torque during installation to ensure that they will provide the necessary support. In the event the Project’s contractor failed to reach the required installation torque, the Bid Specifications outlined three options: (1) install the Helical Pile deeper using additional extension sections (“Option 1”); (2) remove the existing Helical Pile and install a new one with additional and/or larger diameter helix plates (“Option 2”); or (3) de-rate the load capacity of the Helical Pile and install additional Helical Pile(s) (“Option 3”). Option 3 also provided that the “Contractor shall reimburse owner for all costs of the Project Design Engineer for any foundation redesigns.” On February 10, 2011, the City accepted Revoli’s bid to serve as the General Contractor for the Project. Revoli subcontracted G. Donaldson Construction (“Donaldson”) to install the helical piles, and Donaldson hired Franklin Grynkewicz (“Grynkewicz”), the founder and sole employee of FGG Consulting, to determine the size and number of helix plates‘ that Donaldson should use to comply with the Bid Specifications. Richard Wilhelmsen (“Wilhelmsen”), Donaldson’s Division Manager, testified that before Donaldson hired Grynkewicz, he “assumed” that “someone” reviewed Kleinfelder’s boring logs. Grynkewicz testified that he designed the 3 Torque is the tendency of a force to rotate an object about an axis. To determine the proper installation torque, the helical pile designer considers the weight of the structure the helical pile must support and select a torque factor. A torque factor is a number between two and twenty that is based on soil conditions, the shaft size of the pile, and the pile manufacturer’s recommendations. 4 The Bid Specifications define a “helix plate” as a “[g]enerally round steel plate formed into ramped spiral. The helical shape provides the means to install the helical pile, plus the plate transfers load to soil in end bearing.” 3helical piles for the Project based solely on the Kleinfelder boring logs. Grynkewicz added that “[o]ne of the things that was of concern” to him during the design process was that the Kleinfelder boring logs “didn’t go deep enough.” Grynkewicz testified that he believed he had designed the helical piles “based upon insufficient information.” Kleinfelder hired a geotechnical engineering firm, Brierley Associates, LLC (“Brierley”) to review Grynkewicz’s calculations. Brierley’s geotechnical engineer, Jay Perkins (“Perkins”), approved the calculations after Grynkewicz incorporated a number of revisions. Based on these calculations, Donaldson was required to attain an installation torque of 5,400 feet per pound. On March 30, 2011, Revoli’s project manager, Alfredo Palumbo (“Palumbo”) wrote a letter to Charles Serpa (“Serpa”), a civil engineer from the City’s Department of Public Works, to notify Serpa that Donaldson had attempted to install helical piles at five different locations at the Project site, but could “not achieve the proper torque necessary to meet the design criteria which was based on [the Kleinfelder soil borings].” The letter attributed this issue to “differing site conditions” and continued that [Donaldson] . . . advised Mr. Perkins that two options were available to resolve the changed conditions encountered which included drilling additional borings to determine the depth of rock and change the pile design to an end bearing design . . As of the end of Monday March 28, 2011 Revoli and [Donaldson] have suspended operations until such time that direction is given on how to proceed In accordance with the contract General Conditions Section 10.05 please be advised that Revoli is hereby giving notice that a change in sub surface conditions exists as described above. ... Revoli will document the data required to justify an equitable adjustment to the contract price as per the contract documents and MGL Chapter 30/39N. Robert Beshara (“Beshara”), the City Engineer and Superintendent of Public Works responded to Palumbo’s letter on March 31, 2011. Beshara stated that Revoli “presented no evidence” to support its assertion that there were “differing site conditions,” and that Revoli’s“Notice of Change in Soil Conditions” was rejected “as having no documentation to support the Notice.” Beshara’s letter stated that Revoli’s “suspension of operations in is [sic] violation of the Contract Specifications” and directed Revoli to Options 1, 2, and 3 of the Bid Specifications. On April 1, 2011, Donaldson performed its own soil borings. During his deposition, Perkins testified that Donaldson’s boring logs (“Donaldson boring logs”) lacked quality control because a “driller” who was “not educated in the field of geology and not qualified to classify soils” performed them Perkins also stated that the descriptions in the Donaldson boring logs were not in accordance with the standards required by the American Society for Testing and Materials. Perkins concluded that the Donaldson boring logs failed to evidence differing subsurface conditions. During his deposition, Grynkewicz also reviewed the Donaldson boring logs. Like Perkins, Grynkewicz concluded that the Donaldson boring logs evidenced soil conditions reasonably consistent with those contemplated in the contract specifications. Likewise, Revoli’s president, Shawqi Alsarabi (“Alsarabi”), testified that neither Revoli nor Donaldson were geotechnical engineering firms qualified to determine whether the subsurface conditions differed, and that even so, he did not personally believe that there were differing subsurface conditions at the Project site. On April 5, 2011, Palumbo wrote a letter to Beshara, which stated that Donaldson had exhausted Options 1 and 2, and was still unable to achieve the required installation torque of 5,400 feet per pound. Palumbo’s letter continued that the contract price for the helical piles would triple if Option 3 is carried out. Revoli recommends that it would be more economical for the City to change to an end bearing pile instead of adding more piles as per option 3 . . . and Revoli further requests that the attached information and design from Donaldson for end bearing piles be reviewed by the City.' Beshara responded to Revoli’s letter the same day. Beshara stated that the contract did “not provide for additional piles to overcome a failure to reach the required torque values,” but agreed “that a change to an end bearing pile would be a more economical solution for [Revoli] than any of the options available under the Contract.”* Beshara also stated that Revoli had still “not provided any evidence to support [its] statement of ‘differing site conditions,” and that the data from the Donaldson boring logs “confirm[ed] the gravel and sand stratum depicted” in the Kleinfelder boring logs. Beshara said that the City would “consider” Revoli’s proposal for an end bearing pile support system and asked Revoli to submit shop drawings of its proposed design, signed by a Massachusetts physical engineer. . On April 7, 2011, a Massachusetts physical engineer approved Revoli’s design for an end bearing support system. The City stipulates that it agreed to the end bearing design, but the record does not indicate who approved the design on behalf of the City, precisely when, or whether the approval was oral or written. It is undisputed, however, that Donaldson resumed installing the helical piles using the end-bearing design on April 12, 2011.¢ On April 19, 2011, Atlas Systems of New England (“Atlas”) performed an independent third-party review of Donaldson’s helical pile installation procedures. Beshara testified that Kleinfelder hired Atlas in response to questions raised by unspecified parties regarding the veracity of Donaldson’s installation methods and torque readings. Atlas installed its own torque monitoring device to Donaldson’s torque motor in a manner that allowed it to read Donaldson’s torque monitoring device at the same time. Atlas found that the readings on Donaldson’s monitoring device did not correlate to the readings on its own monitoring device or “to any 5 The City points out in its memorandum that Beshara concluded an end bearing system would be less expensive for Revoli because Option 3 would require Revoli to bear the costs of a foundation redesign incorporating the additional piles. 6 The end-bearing design required Revoli to cut the tips off the helical piles to allow them to rest on flat bedrock. 6rational torque readings for the given soil profile.” Atlas concluded that Donaldson’s torque monitoring device “was not properly calibrated and or functioning to accurately record the installation torque values.” Donaldson finished installing the helical piles on April 25, 2011. It is unclear when Revoli completed the Project, but the parties agree that it was finished on time, and Revoli’s contract with the City required it to be substantially complete by April 29, 2011. The City paid Revoli $646,421.86 for its work. On May 27, 2011, Palumbo sent a letter to Serpa that stated, in relevant part: As a result of the helical pile delay in installation, Revoli had incurred downtime on its equipments [sic] which were not able to perform work due to the delay caused in the redesign of the piles. On this date Revoli has received a change order from Donaldson requesting compensation for the additional costs incurred to complete the helical piles on this project due to a change in sub surface conditions. Donaldson’s claim is that the borings provided in the contract for which the helical pile design was based upon were not accurate and the differing soil conditions found in the field prevented the helical piles from achieving the required torque and further forcing a redesign of the helical pile. . . . Revoli submits Donaldson’s claim due to the change in sub surface conditions they claimed to have encountered as set forth in the contract and MGL Chapter 30/39N. Revoli submits this change order request due to the differing subsurface conditions claim made by Donaldson and hence has attached a copy in its entirety as a formal change order request. Kindly formulate a change order in the amount of $160,805.37 and add 120 hours or 15 days to the contract completion time and forward to this office for execution. On July 28, 2011, after the City denied Revoli’s May 27, 2011 request, Palumbo wrote a letter to Beshara. In his letter, Palumbo repeated Revoli’s claim that Revoli and Donaldson “incurred additional costs due to the delay and additional materials necessary to install the helical piles to refusal. This outcome was the result of a change in subsurface conditions whichprevented the helical piles from achieving the required torques as originally designed by G. Donaldson and approved by the Engineer.” Il. Contract The terms of Revoli’s contract with the City are set forth in a series of documents referred to as the “Contract Documents.” The Contract Documents the court reviewed include: the Bid Specifications; a document simply titled “Agreement,” which outlines the general terms of the City’s contract with Revoli; and a document titled “Standard General Conditions of the Construction Contract” (“General Conditions”). A. Reliance on Kleinfelder Boring Log Data All of the Contract Documents contain provisions that limited Revoli’s ability to rely on the Kleinfelder boring logs. The Bid Specifications warned prospective contractors that they were required to interpret such data according to his or her own judgment and acknowledge [] that he or she is not relying upon the same as accurately describing the subsurface conditions which may be found to exist. The Contractor further acknowledges that he or she assumes all risk contingent upon the nature of the subsurface conditions, to be actually encountered in performing the work covered by the Contract, even though such actual conditions may result in the Contractor performing more or less work than he originally anticipated. The Bid Specifications required Revoli to acknowledge that it was “responsible for performing any additional investigations . . . necessary to bid and to perform the work,” and that it understood “that information relative to subsurface and other conditions . . . has been furnished only for his information and convenience without any warranty or guarantee, expressed or implied, that the subsurface and/or other conditions . . . actually encountered will be the same as those shown on the Drawings or in any of the other Contract Documents and he agrees that he shall not use or be entitled to use any such information made available to him through theContract Documents . . . as a basis of or ground for any claim against the Owner or the Engineer arising from or by reason of any variance which may exist between the aforesaid information . . . and the subsurface and/or other conditions . . . actually encountered during construction work, and he has made due allowance therefore in this BID .. . .” Likewise, the General Conditions contained the following provision: 4.02 Subsurface and Physical Conditions A. Reports and Drawings: The Supplementary Conditions Identify: 1, those reports of explorations and tests of subsurface conditions at or contiguous to the Site that ENGINEER has used in preparing the Contract Documents; and those drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground facilities) that ENGINEER has used in preparing the Contract Documents. Limited Reliance by CONTRACTOR on Technical Data Authorized: CONTRACTOR may rely upon the general accuracy of the ‘technical data’ contained in such reports and drawings, but such reports and drawings are not Contract Documents. .. . Except for such reliance on such ‘technical data,” CONTRACTOR may not rely upon or make and Claim against OWNER, ENGINEER, or any of ENGINEER’s Consultants with respect to: 1, the completeness of such reports and drawings for CONTRACTOR’s purposes .... other data, interpretations opinions, and information contained in such reports or shown indicated in such drawings; or any CONTRACTOR interpretation of or conclusion drawn form any ‘technical data’ or any such other data, interpretations opinions, or information. Additionally, the Agreement required Revoli to acknowledge that it had “carefully studied all reports of explorations and tests of subsurface conditions” at the Project site and“accept[ed] the determination . . . of the Supplementary Conditions of the extent of the ‘technical data’ contained in such reports and drawings upon which CONTRACTOR is entitled to rely as provided in paragraph 4.02 of the General Conditions .:..” The Agreement continued that B. CONTRACTOR acknowledges that OWNER and ENGINEER do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Contract Documents with respect to Underground Facilities at or contiguous to the [Project] site. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so) all such additional supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface, and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance, or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by CONTRACTOR .... CONTRACTOR does not consider that any additional examinations, investigations, explorations, tests, studies, or data are necessary for the performance and furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents. Unexpected Subsurface Conditions The Bid Specifications required Revoli to notify the City and cease helical pile installation in areas where discrepancies in site conditions are found until they are resolved. The Bid Specifications further provided that all costs associated with site condition discrepancies are the responsibility of the City. Likewise, paragraph 4.03 of the General Conditions required Revoli to cease helical pile installation and notify Kleinfelder and the City in writing upon discovery of differing subsurface or physical conditions at the Project site. This section stated that differing subsurface or physical conditions are conditions: (1) that establish the “technical data” upon which Revoli was entitled to rely “is materially inaccurate;” (2) “of such a nature to require a change in the Contract Documents”; (3) “differ[] materially from that shown or indicated in the Contract Documents;” or (4) “of an unusual nature, and differ[] materially from conditions ordinarily encountered and 10generally recognized as inherent in work of the character provided for in the Contract Documents.” Paragraph 4.03 continued that upon receipt of written notice of purported differing site conditions, Kleinfelder “will promptly review the pertinent site condition” and determine the necessity of additional exploration or tests. c Changes Several provisions in the General Conditions governed changes to the contract documents, price, and time for completion. These provisions are excerpted in relevant part below: 3.04 4.03 Amending and Supplementing Contract Documents The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof in one or more of the following ways: (i) a Written Amendment; (ii) a Change Order; or (iii) a Work Change Directive. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, by . . . (i) a Field order;! (ii) ENGINEER’S approval of a shop drawing or sample; or (iii) ENGINEER’s written interpretation or clarification. Differing Subsurface or Physical Conditions Possible Price and Times Adjustments 1. The Contract Price . .. will be equitably adjusted to the extent that the existence of such differing subsurface or physical condition causes an increase or decrease in CONTRACTOR’s cost of, or time required for, performance of the Work; subject, however, to the following: 7 The General Conditions define a “field order” as “[a] written order issued by ENGINEER which requires minor changes in the Work but which does not involve a change in the Contract Price or the Contract Times.” 11a. such condition must meet any one or more of the categories described in paragraph 4.03A .... 2. CONTRACTOR shall not be entitled to any adjustment in the Contract Price .. . if: b. the existence of such condition could reasonably have been discovered or revealed as a result of any examination, investigation, exploration, test, or study of the Site and contiguous areas required by the Bidding Requirements or Contract Documents to be conducted by or for CONTRACTOR prior to CONTRACTOR’s making such final commitment . 10.01 Authorized Changes in the Work A. .... [the City] may, at any time or from time to time, order additions, deletions, or revisions in the Work by a Written Amendment, #! a Change Order, ! or a Work Change Directive. !"0] Upon receipt of any such document, CONTRACTOR shall promptly proceed with the Work involved... . 10.02 Unauthorized Changes in the Work A. CONTRACTOR shall not be entitled to an increase in the Contract Price . . . with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented as provided in paragraph 3.04.... The General Conditions define a “written amendment” as “[a] written statement modifying the Contract Documents, signed by OWNER and CONTRACTOR on or after the Effective Date of the Agreement and normally dealing with the nonengineering or nontechnical rather than strictly construction-related aspects of the Contract Documents. The General Conditions define a “change order” as “[a] document recommended by ENGINEER which is signed by CONTRACTOR and OWNER and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price ....” The General Conditions define a “work change directive” as “[a] written statement to CONTRACTOR issued on or after the Effective Date of the Agreement and signed by OWNER and recommended by ENGINEER ordering an addition, deletion, or revision in the Work, or responding to differing or unforeseen subsurface or physical conditions under which the Work is to be performed .... A Work Change Directive will not change the Contract Price . . . but is evidence that the parties expect that the change ordered or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price .. 1212.06 Delay Damages A. In no event shall OWNER or ENGINEER be liable to CONTRACTOR . . . for damages arising out of or resulting from . . . delays caused by or within the control of CONTRACTOR. DISCUSSION IL Standard Summary judgment shall be granted where there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. Mass. R. Civ P. 56(c). See Cassesso v. Commissioner of Corr., 390 Mass. 419, 422 (1983); Community Nat’l Bank v. Dawes, 369 Mass. 550, 553 (1976). The moving party bears the burden of establishing that there is no dispute of material fact on every relevant issue. See Sullivan v. Liberty Mut. Ins. Co., 444 Mass. 34, 39 (2005). A party moving for summary judgment who does not bear the burden of proof at trial may demonstrate the absence of a genuine dispute of material fact either by submitting affirmative evidence negating an essential element of the non-moving party’s case, or by showing that the non-moving party has no reasonable expectation of proving an essential element of its case at trial. See Flesner v. Technical Commce’ns Corp., 410 Mass. 805, 809 (1991); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). When the court is faced with cross-motions, as it is here, its analysis is guided by which party has the burden on the issues before the court. See Epstein, 77 Mass. App. Ct. at 756. The fact that one party’s motion fails does not mean that the cross motion necessarily succeeds. See id. It. Analysis The record reveals that from the time of Revoli’s alleged discovery of differing subsurface conditions in March 2011, until it filed its Complaint in July 2012, Revoli has argued that it is entitled to an equitable adjustment of the contract price pursuant to the contract terms 13regarding differing subsurface conditions and the provisions of G. L. c. 30, § 39N (requiring an equitable adjustment to the price of public construction contracts where contractor discovers differing subsurface or latent physica! conditions). In the memorandum in support of its motion for summary judgment, Revoli for the first time argues that whether there were different subsurface conditions at the Project site is irrelevant and acknowledges that “no party has actually determined why the Installation Torque could not be achieved.” Throughout the same memorandum, however, Revoli maintains that because “the subsurface conditions present at the site did not allow Revoli to achieve the necessary Installation Torque,” the City is responsible for the costs Revoli incurred by switching to the end bearing support system. A. Differing Subsurface Conditions To the extent that Revoli still relies on the assertion that differing subsurface conditions warrant an equitable adjustment to the contract price, the court does not agree." As the City correctly contends, there is no evidence in the summary judgment record to suggest that the subsurface conditions Revoli encountered differed in any way from what was anticipated in the Kleinfelder boring logs. See Celeo Construction Corp. v. Avon, 87 Mass. App. Ct. 132, 135 (2015). Notably, Revoli’s president testified that he agrees that the subsurface conditions were not different. Moreover, Atlas concluded that rather than encountering differing subsurface conditions, Donaldson’s apparent inability to achieve the required torque was a result of improperly calibrated torque monitoring equipment. Further, Perkins and Grynkewicz, who are both geotechnical engineers, testified that the conditions revealed by the Donaldson boring logs "Although Revoli asserts that differing subsurface conditions are now irrelevant to its claim, it maintains that Paragraph 3.1D of Section 02466 of the Bid Specifications supports its claim for breach because that provision required the City to pay “all costs associated with unresolved discrepancies” in the site conditions. 14were similar and consistent with the conditions contemplated in the contract documents and the Kleinfelder boring logs. ‘ Revoli attempts to counter this evidence by citing to the portion of Wilhelmsen’s deposition during which Wilhelmsen offered to compare the Kleinfelder and Donaldson boring logs to determine whether there were material differences between them. After completing his review, Wilhelmsen testified that he observed “some substantial differences” between the two boring logs. Wilhelmsen’s testimony is unpersuasive. The interpretation of soil boring data “is beyond the common knowledge or understanding of the lay juror,” and requires expert testimony. See Commonwealth v. Sands, 424 Mass. 184, 186 (1997) (quotation omitted). The court has broad discretion to determine whether a witness has a proper foundation upon which to render an opinion on the matter in dispute. Louise Caroline Nursing Home, Inc. v. Dix Constr. Corp., 362 Mass. 306, 309 (1972). The court finds that Wilhelmsen, who is not an engineer, and testificd that he hired geotechnical engineers to perform the same analysis of the boring logs that he purported to perform himself during his deposition, was not qualified to render an opinion on the meaning of the Kleinfelder and Donaldson soil borings. Revoli alternately contends that soil borings are irrelevant to an analysis of whether differing subsurface conditions were present at the Project site, and points to Sutton Corp. v. Metropolitan District Commission, 423 Mass. 200, 206 (1996), in support. In Sutton, the court held that subsurface conditions are materially different where they differ from “those conditions ordinarily encountered and generally recognized as inherent in work of the character provided for in the plans and contract documents.” Revoli’s reliance on Sutton is misplaced. Here, unlike the parties in Sutton, the parties do not agree that there were differing subsurface conditions at 15the Project site. 423 Mass. at 203 n.5. Further, not only has Revoli failed to set forth any credible evidence that it encountered subsurface conditions that differed from those “ordinarily encountered” while performing similar work, but even if Revoli had set forth such evidence, it expressly assumed the risk of differing conditions when it executed the Contract Documents. Specifically, the Contract Documents expressly disclaimed the stated nature of the subsurface conditions and required Revoli to “assume[] all risk contingent upon the nature of the subsurface conditions, to be actually encountered in performing the work covered by the Contract, even though such actual conditions may result in the Contractor performing more or less work than he originally anticipated.” Implicit in this language was the forewarning that conditions that differed from the contract specifications could be contemplated and should be considered by Revoli when it computed its bid. Similar disclaimers appeared in the Bid Specifications, the Agreement, and the General Conditions. When a plaintiff has been cautioned, in writing, about a condition of a contract it may not then ignore the warning. See Page v. Frazier, 388 Mass. 55, 66 (1983). Revoli must bear the consequences of its choice, after disclosure by the City, to elect the riskier path of not doing its own investigation before bidding on the Project. Revoli contends that the foregoing disclaimers are in conflict with Paragraph 4.02 of the General Conditions, which provides that the contractor may rely on the “general accuracy” of the “technical data” provided in the Kleinfelder boring logs. Revoli is incorrect. A provision permitting contractors to rely on the accuracy of data, such as Paragraph 4.02, is not the same as a provision permitting contractors to rely on the sufficiency of data. See Callahan v. First, Congregational Church of Haverhill, 441 Mass. 699, 710-711 (2004) (distinguishing “accuracy” and “sufficiency”); see also Southern Union Co. v. Department of Pub. Utils., 458 Mass. 812, 16820 (2011) (“The court interprets a contract that is free from ambiguity according to its plain meaning.”). Paragraph 4.02 expressly disclaimed the completeness of Kleinfelder’s boring logs as well any opinions or conclusions that Revoli may have drawn therefrom. Moreover, the Agreement required Revoli to acknowledge that it did “not consider that any additional examinations, investigations, explorations, tests, studies, or data are necessary for the performance and furnishing of the Work at the Contract Price... .” Despite these extensive disclaimers, Alsarabi testified that Revoli did not hire or consult with any geotechnical engineers in order to produce its bid. ; Revoli additionally avers that the technical data Paragraph 4.02 permitted it to rely on was inaccurate, citing Grynkewicz’s testimony that Kleinfelder’s soil borings were not deep enough. This argument is without merit. Grynkewicz’s testimony does not evidence that Kleinfelder’s boring logs were inaccurate, but that Kleinfelder’s soil borings were insufficient to gather the amount of data needed to design a helical pile support system. As stated, it was up to Revoli to consider whether Kleinfelder’s boring logs provided sufficient data to bid on accurately and complete the Project. In the face of such evidence, the court finds that Revoli has failed to overcome the City’s showing that no reasonable juror could find that Revoli encountered differing subsurface conditions and is therefore entitled to recover on that basis pursuant to the Contract Documents or G. L. c. 30, § 39N. Flesner, 410 Mass. at 809. B. Other Alleged Breaches Revoli argues it is entitled to damages for various breaches of contract that are unrelated to the City’s response to its claim of differing subsurface conditions. The City counters that 17summary judgment is appropriate on Revoli’s claims for breach, because the undisputed facts reveal that Revoli has no reasonable expectation of proving any of the City’s purported breaches at trial. See Flesner, 410 Mass. at 809. The City is correct. _ Revoli argues that the City first breached the terms of the Contract Documents when the City “jefused” to pay for the additional piles needed to pursue Option 3. Revoli suggests that as a result of the City’s purported refusal to pay for additional piles, the City “requested” a change from the helical support system to the end bearing support system. Revoli argues that when the City refused to issue a change order following its purported request, it breached Paragraph 10.01 (A) of the General Conditions, The court does not agree. ' Article 10.01(A) provides that the City “may, at any time or from time to time, order additions, deletions, or revisions in the Work by a Written Amendment, a Change Order, or a Work Change Directive. Upon receipt of any such document, CONTRACTOR shall promptly proceed with the Work involved . ...” There is no evidence in the summary judgment record that would support a reasonable conclusion that the City “ordered” the end bearing pile design. See Commonwealth v. Lopez, 451 Mass. 608, 610 (2008) (defining an “order” as a command); Crane Const. Co. v. Commonwealth, 290 Mass. 249, 253 (1935) (whether a writing constitutes a written order to perform work is a question of law). To the contrary, Palumbo’s March 30, 2011 letter to Serpa and Beshara’s Apri! 5, 2011 letter to Revoli reveal that Revoli recommended the end beating pile system in lieu of implementing Option 3 before Beshara indicated that the City would not pay for additional piles. ' Additionally, the summary judgment record does not contain any evidence that the City issued a written amendment, change order, or work change directive. Undoubtedly, written approval provisions are “onerous” and tend to slow down the work, however, uniess such a 18provision has been modified or waived, “a contractor who goes ahead without such approval does so at his peril.” Savignano v. Gloucester Housing Auth., 344 Mass. 668, 672 (1962); see Johnson v. Norcross Bros. Co., 209 Mass. 445, 446-447 (1911) (“The purpose of the provision that the defendant shall not be held to pay anything either for changes, additions or other extra work unless ordered in writing is plain. The provision manifestly was intended to prevent any future controversy likely to arise as to the liability of the general contractor for work so done, and it is a useful and reasonable provision.”). ._ C. Bad Faith , Although Revoli has not brought a separate claim for breach of the implied covenant of good faith and fair dealing, the court will address Revoli’s contention that the City has not acted in good faith “in an astounding attempt to avoid paying Revoli.” Revoli avers that “[w]hen it became clear that the helical piles could not be installed in accordance with the contract specifications [the City] immediately started writing letters disclaiming any involvement in the Project” and “refus[ed] to provide even the most basic direction as to how Revoli should proceed.” The record does not contain any evidence that supports these assertions. Rather, the evidence shows that the City typically answered Revoli’s correspondence within a day, and repeatedly directed Revoli to the responsive provisions of the Contract Documents. Revoli does not state what additional actions the City should have taken, nor can the court presume what they might be. Until filing its Motion for Summary Judgment, Revoli maintained that differing subsurface conditions caused its damages. Kleinfelder and the City requested evidence of such, but Revoli failed to produce any. When Kleinfelder performed its own investigation, it determined that the Donaldson could not achieve the required torque because it had not properly 19calibrated its equipment. Paragraph 12.06 of the General Conditions provides that the contract price will not be adjusted for delays or damages within the contractor’s control. Absent any evidence of differing subsurface conditions, the only reasonable conclusion supported by the evidence in the record is that the delays and damages Revoli incurred were due to factors within its control. ’ Revoli’s assertion that the detailed nature of the Bid Specifications rendered any design flaws outside of its control is unpersuasive. When one enters into a contract “to erect a structure in accordance with plans and specifications, which are open to inspection, without express provision touching the subject, there is no implied warranty or agreement on the part of the owner, in the absence of circumstances which by necessary intendment are the equivalent of a warranty or agreement, that the work can be done according to the plans and specifications, or that, if so done, if will be safe. It is the duty of one, who proposes to enter into a building contract to examine the contract, plans and specifications, and to determine whether it is possible to do the work before entering into the engagement, or to insist upon some stipulation covering that matter. If, without a special agreement upon that point, he makes a general contract without fraud or mutual mistake, he has bound himself to do the work. . .. Having made his contract, he must fulfill it or bear the consequences of a breach.” N.J. Magnam Co. v. Fuller, 222 Mass. 530, 532 (1916). The City and Kleinfelder relied on Revoli’s experience and knowledge to properly design and install a helical pile foundation system. Per the Bid Specifications, Revoli agreed to furnish “all necessary engineering and design services, supervision, labor, tools, materials, and equipment to perform all work necessary to provide a helical pile foundation system . . . .” (Emphasis added). The end bearing system was not an addition to these requirements. Compare 20Glynn v. Gloucester, 9 Mass. App. Ct. 454, 460-461 (1980) (holding that where “actions or requirements” of a public agency “necessitate changes in the work as it progresses,” the public authority must make a good faith effort to “compensate the contractor for bona fide extras”). Based on the foregoing, Revoli has failed to demonstrate that the City’s decision not to issue a change order was in bad faith. D. = Statutory Relief Revoli also contends that once the City issued “an approved deviation from the original plans and specifications,” it was “statutorily required to issue some form of confirmatory change order” pursuant to G. L. c. 30, § 391. Section 391 prohibits contractors from making “wilful and substantial deviation[s]” from the specifications of a public construction contract, “unless authorized in writing by the awarding authority or by the engineer or architect in charge of the work.” Within thirty days following a written authorization, the awarding authority must issue a certificate detailing the reasons for the change, whether an equitable adjustment of the contract price was agreed upon, and if so; the amount of the adjustment. As stated, the record does not contain any evidence that the City authorized the change from a helical pile system to an end bearing system by a writing. It follows that G. L. c. 30, § 391 is inapplicable to the present case." Cf. Morse v. Boston, 253 Mass. 247, 253 (1925) (“The terms and purpose of the 22 Assuming, arguendo that the end bearing system was an addition to the work, Revoli’s claim would still fail to withstand the Defendants’ Motion for Summary Judgment because it has not set forth any evidence of compliance with the requirements of G. L. c. 44, § 31. See Murphy v. Brockton, 364 Mass. 377, 381 (1973) (finding contractor was bound to take notice of G. L. c. 44, § 31 requirements and denying recovery to contractor who performed work in excess of funds appropriated for subject contract “in anticipation of a later appropriation,” which the city council ultimately declined to authorize); Glynn, 9 Mass. App. Ct. at 461-462. 13, According to the record, the only significant difference between the helical pile and end bearing system was that the ends of the helical piles were blunted. The court infers that the City and Kleinfelder considered this change a “minor variation{] or deviation[]” pursuant to Paragraph 3.04(B) of the General Conditions, which permits contractors to proceed with minor variations and deviations from the contract requirements pursuant to the “ENGINEER’s approval of a Shop Drawing or Sample.” According to the record, Revoli provided the City a shop drawing of its proposed end bearing foundation design before it was approved. There is nothing in the 21governing statutes constitute in themselves a restriction of the power to amend and alter a contract once made in accordance therewith.”). -E. Quantum Meruit Lastly, Revoli seeks damages in quantum meruit. “Quantum meruit is a theory of recovery, not a cause of action. It is a claim independent of an assertion for damages under the contract, although both claims have as a common basis the contract itself. Recovery under this theory is derived from the principles of equity and fairness and is allowed whether there is substantial performance but not full completion of the contract.” J.A. Sullivan Corp. v. Commonwealth, 397 Mass. 789, 793-794 (1986) (citation omitted). A contractor may recover in quantum meruit, if it “can prove both substantial performance of the contract and an endeavor on. his part in good faith to perform fully, and the burden is upon him to prove both. In the absence of special exculpating circumstances an intentional departure from the precise requirements of the contract is not consistent with good faith in the endeavor fully to perform it and unless such departure is so trifling as to fall within the rule de minimis, it bars all recovery.” Andre v. Maguire, 305 Mass. 515, 516 (1940). To determine whether Revoli substantially performed under the contract, the court must “examine the evidence in reference to the entire contract, what had been done, and what had been omitted.” Id. at 671. As a general contractor, Revoli had a duty to use reasonable care in performing its responsibilities under the Contract Documents. See Anthony’s Pier Four, Inc. v. Crandall Dry Dock Engineers, Inc., 396 Mass. 818, 823 (1986). Such obligations extended to performing an Contract Documents that indicates the engincer’s approval of a shop drawing or sample requires a writing. See Lawrence-Lynch Corp. v. Department of Environmental Mgmt., 392 Mass. 681, 684 (1984) (“Minor deviations from the plans or specification, however, may be authorized orally.”). 22analysis of subsurface conditions to acquire sufficient data upon which to design the helical piles and installing the helical piles with properly calibrated equipment. Undisputed evidence in the summary judgment record reveals that Revoli failed to meet these obligations. It follows that Revoli has failed to sustain its burden to show that it substantially performed the contract and endeavored in good faith to perform fully. Based on the foregoing, Revoli is not entitled to recover on its claim for quantum meruit. ORDER For the foregoing reasons, the Defendants’ Motion for Summary Judgment is Rosalind H. Miller Justice of the Superior Court ALLOWED and Revoli’s Motion for Partial Summary Judgment is DENIED. Date: December 7, 2015 23