arrow left
arrow right
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
  • AGGREGATE TECHNOLOGIES INC vs. GOLDSHIRE DEVELOPERS LLC BREACH OF CONTRACT document preview
						
                                

Preview

CAUSE NO. 2012 34382 AGGREGATE TECHNOLOGIES, INC. IN THE DISTRICT COURT OF HARRIS COUNTY, TEXAS GOLDSHIRE DEVELOPERS, LLC, § etal 152nd J UDICIAL DISTRICT DEFENDANTS’ RESPONSE IN OPPOSITION TO MOTION FOR ENTRY OF J UDGMENT Defendants submit that plaintiff is not entitled to entry of judgment for the full amount it has requested, and in support would show: No Breach of Contract J udgment for Payment Application No. 8 Defendants agree that, based upon the jury’s verdict (without admitting or co ceding that the verdict itself was proper), ATI would be entitled to judgment for the amounts represented by its ayment Applications Nos. 6 and 7 in the amount of $98,831.65However, for the reasons set forth in Defendants’ Motion to Disregard J ury Answers and forJ udgment N.O.V. (which is incorporated by reference for all purposes), ATI is not entitled to judgment on its breach of contract claim for ayment Application No. 8 because ATI's President, Ronnie W , conclusively admitted that there was no agreement by Goldshire to pay those amounts. Without an agreement to pay those amounts, (which exceed the amount of the original agreed contract price) there was no contract to pay any additional amounts for the additional work done by ATI on Bents 38 and 40. Because there was no contract to pay those amounts, and no jury question was submi ted that could have attempted to establish the existence of such an agreement, Page of ATI is not entitled to judgment for breach of contract for the amounts represented by Payment pplication No. 8. No Quantum Meruit J udgment for Payment Application No. 8 ATI is further not entitled to judgment on its quantum meruit claim for Payment Application No. 8 because the subject matter of that payment application was already the subject of its express contract with Goldshire. It was undisputed that ATI was obl gated by its agreement with Goldshire to completely remove Bents 38 and 40, including the footings. It is fu ther undisputed that the work and associated charges represented by Pa ment A plic tion No. 8 were all related to costs incurred by ATI in connection with the remo al of Bents 38 and 40. As such, the subject matter of payment application No. 8 was aready included within the express contract between ATI and Goldshire. ment cation No. 8 is nothing more or less than an attempt to recover cost ove runs by ATI for work it was already required to complete. Even if, as Mr. Wills admitted, Gol shire did not agree to pay these additional costs, the work was still already required to be co pleted under the original contract. No quantum meruit claim exists merely b cause the work to be completed cost ATI more than the original contract price. No Payment Bond J udgm ent for Payment Application No. 8 Finally, ATI is not entitled to any judgment on its payment bond claim. Payment bonds are limited only to an undertaking by the sureties to pay the amount of the co tract price owed to the claimant. The payment bond does not apply to or extend to amounts not due and owing under the construction contract. ATI admitted that there was no contract modification or agreement to pay the amount of Payment Application No. 8, which is undisputedly more than the amount of the origina contract price and the Page of amount that the jury determined was a perfected bond claim. The payment bond statute (or, to be more precise, Chapter 2253 of the Texas Government Code) does not apply or extend to quantum meruit recoveries as a matter of law. Where there is no basis fora breach of contract claim to ATI, its quantum meruit/compensable work claim may be e tered, if at all, only as against Goldshire, and not against the surety defendants on the payment bond. Defendants accordingly pray that any judgment in favor of ATI be limited only to the amounts represented by Payment Applications Nos. 6 and 7; that no judgment be entere in favor of ATI on the payment bond claim against any of the bond/surety d fendants; and that any attorneys’ fees, interest, and costs be limited in accordance with that judgment. Respectfully submitted, FFICE ATTE. UBIN /s/ MattE. Rubin Matt E. Rubin State Bar No. 17361620 12 Greenway Plaza, Suite 1100 Houston, TX 77046 1201 Telephone: 713 335 0300 Facsimile: 713 425 4999 Email: mrubin@ mrubinlaw.com ATTORNEY FOR DEFENDANTS Page of Certificate of Service | hereby certify that on the day of December, 2014, a true and correct copy of the foregoing was served upon counsel of record by electronic delivery through the State of Texas e filing system, addressed as follows: William B. Westcott William B. Davis ANDREWS MYERS, P.C. 3900 Essex Lane, Suite 800 Houston, TX 77027 Attorneys for ATI /s/ MattE. Rubin Page of