ANALYSIS

Plaintiff J.F. Shea Construction, Inc.’s Motions to Compel Responses to Form Interrogatories, Special Interrogatories, and Requests for Production of Documents are GRANTED, in part, and DENIED, in part. Defendant is ordered to provide responses within 20 days.

Plaintiff J.F. Shea Construction, Inc. (“Plaintiff”), moves the court for orders requiring Defendant U.S. Controls, Inc. (“Defendant”) to provide verified responses to its form interrogatories (sets 1 & 2), special interrogatories (set 2), and request for production of documents (sets 1 & 2).

Code of Civil Procedure sections 2030.290(b) and 2031.300(b) allow the propounding party to file a motion to compel responses to interrogatories and document demands if a response has not been received. If responses are untimely, responding party waives objections. (CCP §§ 2030.290(a) and 2031.300(a).)

Set One

On or about June 29, 2018, Plaintiff served its Form Interrogatories, Set One and Request for Production of Documents,