TENTATIVE ORDER DENYING MOTION FOR SUMMARY ADJUDICATION OF THE CAUSE OF ACTION FOR BREACH OF CONTRACT

Dept. T

8:30 a.m.

September 17, 2020

[TENTATIVE] RULING: DENIED

There are numerous triable issues of fact as to whether there was breach of the contract. For this reason, the motion is denied.

THERE ARE TRIABLE ISSUES OF MATERIAL FACTS WHICH

PREVENT GRANTING OF THE MOTION FOR SUMMARY

ADJUDICATION

The motion cannot be granted because there are triable issues of material facts. The “Submission Summary” dated 2/26/2015 (Pltf’s Exh. 1) shows that the applicant names for the 2015 policy are Carlos Elias Maldonado and Delmont Wilcox dba Maldonado Construction and Associates, a partnership. This is not in dispute.